Heckhuscheid

Heckhuscheid
Solar park with large storage facility in Heckhuscheid: 17,767.5 kWp in the East and West fields, plus 15,470 kWh battery storage with 7.4 MW. Under construction.

Solar park with large storage: 17.8 MWp to be built in Heckhuscheid

Our largest open-air project is currently being built in Heckhuscheid in the Eifel: a Solar park with large storage battery, designed to 17,767.5 kWp in two sub-fields, East and West, supplemented by one Battery storage with 15,470 kWh. The project is currently under construction.

Project at a glance

  • 17,767.5 kWp planned output, divided into the fields East and West
  • Battery storage with 15,470 kWh and 7.4 MW from 39 cubes
  • Location: Heckhuscheid, Eifelkreis Bitburg-Prüm, Rhineland-Palatinate
  • Distribution network operator: Westnetz
  • Status: under construction, Sold storage units to investors

What makes a solar park with large storage units

After a certain size, it is no longer the module area that is the bottleneck, but the grid. A solar park with large storage solutions this problem: The storage system takes up the peak production and delivers it at a staggered time. This allows a higher module output to be operated at a given grid connection point.

In Heckhuscheid, 17,767.5 kWp of production is available for a storage system with a capacity of 10 MW. 15,470 kWh at 7.4 MW Compared to – around two hours of full load. The memory consists of 39 Cubes, That is, prefabricated units that are only installed and connected on site.

Two sub-fields, one project

The system is divided into fields Heckhuscheid Ost and Heckhuscheid West. Such division follows the terrain and the availability of space and allows construction sections to be completed one after the other.

Current status

The project is under construction. The performance figures mentioned are plan values from the current occupancy planning; the final figures will be determined upon commissioning. The battery storage system has already been sold to investors.

Each facility is publicly registered

A solar park with a large storage system also means reporting obligations: Every generation facility is subject to reporting obligations. Market data register of the Federal Network Agency. We will take over the registration as part of the project.

Planning a solar park with a large storage system?

We install the park and storage together at your network connection point and carry out both processes through certification. Contact us.

Medium-voltage technology from Faber E-Tec

The entire medium-voltage technology for this solar park came from within the company’s own group. Faber E-Tec supplied five switchgear cabinets, the transfer station, and the technology for the battery storage system. Thus, the generation, conversion, and storage are all handled in-house—coordinated, planned, manufactured, and commissioned.

Frequently Asked Questions

Because the grid connection forms the bottleneck at a certain size, not the area. The storage system takes up the peak production and delivers it at a staggered time. In Heckhuscheid, the 17,767.5 kWp at one connection point allows for the peak performance that would otherwise not be possible.

Out of 39 Cubes – prefabricated storage units that are delivered completely assembled. On-site they are installed, wired and connected to the medium voltage power supply. The power output is 7.4 MW, the capacity is 15,470 kWh.

Because of terrain and availability of land, Heckhuscheid is divided into East and West fields. Technically speaking, it remains a project with shared network connections; the division also allows for construction sections to be completed one after another.

A plan value originates from the occupancy planning and may still change until completion. The binding performance is fixed upon commissioning and the notification in the market data register. Heckhuscheid is currently under construction.

Yes. In Heckhuscheid, the storage facility has been sold to investors while the park is being further developed. Both components can be considered economically separate, but they must be planned together in terms of the grid connection.